Oman Opens a Hydrogen Auction Built Around AI Data Centres
At COP31, Hydrom opened Round 4, a Dhofar auction that names data centres as the anchor buyers of green power and hydrogen. Three days earlier, plans emerged for a 45MW AI-ready campus at Khazaen. Here's what each announcement means for Oman's push for AI compute.
For the first time, Oman's green hydrogen programme has a named customer in mind, and it's the data centre. On 12 November 2026, at the COP31 climate summit in Antalya, Türkiye, Hydrom opened Round 4 of its national auction. The round is a "Green-Powered Data Centre Hydrogen Auction" in Dhofar, with data centres as the anchor buyers for the renewable power and hydrogen that winning developers produce. Three days earlier, plans were published for a 45MW AI-ready data campus at Khazaen Economic City in Barka. Taken together, the two announcements show the Sultanate trying to solve the hardest part of hosting AI: reliable, clean electricity at scale.
📌 Key Takeaways
- Hydrom's Round 4 auction in Dhofar names data centres as anchor offtakers. Expressions of interest are open until February 2027.
- MTCIT presents hydrogen "firming" as an extra power option for data centres under the Oman Digital Triangle.
- The same day, two Duqm projects won Round 3, targeting about 121,000 tonnes of green hydrogen a year by 2032.
- A 45MW AI and HPC campus is planned at Khazaen in Barka. It could grow to 100MW, with first operations targeted for 2028.
- No investment values have been disclosed, and cost competitiveness is still the big unknown.
⚡ What Hydrom launched at COP31
According to Hydrom's official release, datelined Muscat on 12 November 2026, Round 4 is located in Dhofar. It covers investment opportunities across both energy and digital infrastructure. The idea is to link renewable energy and green hydrogen production to the electricity needs of data centres. Hydrom describes the auction as a "demand-led" approach to allocating projects, one that also builds domestic uses for hydrogen.
Key details so far:
- Location: Dhofar Governorate
- Anchor buyers: Data centres, as offtakers of renewable power and hydrogen
- Deadline: Expressions of interest can be registered until February 2027, according to Oman Observer
- How to apply: Bidders register through Hydrom's official auction platform. Guidelines are published on the Hydrom website
This is a real change of direction. Earlier rounds offered land in Duqm and Dhofar mainly for export-oriented hydrogen and ammonia. Round 4 starts from demand inside Oman instead. Energy Monitor described it as an effort to match renewable and hydrogen output to the power needs of data centres.
"We see growing demand for reliable electricity from the digital economy."
- Eng. Abdulaziz Said Al Shidhani, Managing Director, Hydrom
As TradeArabia reported, Al Shidhani argued that Oman can meet this demand by combining its renewables, its green hydrogen capabilities and its international connectivity.
🖥️ Why data centres, and why hydrogen?
AI data centres need power around the clock, while solar and wind are intermittent. The government's answer is hydrogen "firming": store renewable energy as hydrogen and turn it back into electricity when needed, so supply stays stable.
The Ministry of Transport, Communications and Information Technology (MTCIT) is directly involved. According to TradeArabia, the Ministry of Energy and Minerals and Hydrom are building the offering together with MTCIT under the Oman Digital Triangle, the national framework for attracting large-scale AI and cloud computing.
Dr Seema Al Kaabi, MTCIT's Director General for Sector Stimulation and Future Skills, said the goal is to provide "hydrogen firming as an additional energy option for data centres in Oman." She added that hydrogen, renewables and grid electricity together give investors more clean-energy choices. Oman Observer also reported her saying that the Digital Triangle uses Oman's international connectivity to host AI and cloud projects, and that those projects need reliable, sustainable electricity.
Readers who followed our coverage of Oman's Green AI Alliance and its new technical committee will see the same thinking here: energy policy and AI policy are now being designed together.
🏭 Round 3 closes: two Duqm projects awarded
On the same day, Hydrom awarded the two Round 3 projects in Duqm. Their combined planned output is about 121,000 tonnes of green hydrogen a year by 2032, according to the official release.
| Project | Consortium | Planned output by 2032 | Energy and site |
|---|---|---|---|
| Green ammonium nitrate | Petrogas E&P (Oman), Bio3Energy (Italy) | 625,000 t/yr ammonium nitrate, using about 50,000 t/yr green hydrogen | 1.16 GW renewables, 100 km² plus a proposed 100 km² expansion reserve |
| Green hydrogen and ammonia for export | PLN Indonesia Power Renewables, Alawi Enterprises (Oman), HBA Offshore International (Singapore) | 400,000 t/yr green ammonia | About 1.45 GW solar, 1 GW electrolysis, 100 km² |
The release also sets out the incentives offered in Round 3: a 90% cut in land lease fees during development, lower base royalties in the early production years, and corporate tax exemptions of up to ten years. Hydrom has not yet confirmed whether Round 4 bidders will get the same terms. Prospective bidders should check the Round 4 guidelines directly.
🏗️ Meanwhile in Barka: a 45MW AI-ready campus
The power auction is about future supply. The Khazaen Data Campus (KDC) is about where that power could be used. Oman Observer reported on 9 November that the campus is planned for Khazaen Economic City in Barka, along the Muscat-Al Batinah Expressway.
- Promoters: Dr Thomas Alexander and Dr Aadil Alexander, who are associated with the Al Adrak Group
- Site: About 55,000 square metres
- Capacity: Up to 45MW initially, with possible expansion to 100MW depending on demand
- Target users: International cloud operators, AI developers and high-performance computing (HPC) customers, through carrier-neutral colocation and high-density AI computing
- Standards: Designed around ANSI/TIA-942 Rated 3 and EN 50600 Class 3
- Status: Eight development phases. Governance is complete and the project is now in design, with initial operations targeted for 2028, subject to approvals
Enterprise AM noted that no investment value has been disclosed for the campus.
📊 How Oman's AI data centre pipeline stacks up
| Project | Location | Headline figure | Stage |
|---|---|---|---|
| Khazaen Data Campus | Barka | 45MW, expandable to 100MW | Design and approvals, operations targeted 2028 |
| Mubbadrah-led consortium | Salalah | $3bn, up to 400MW | Proposal stage |
| Yamna, Salalah Al Khadra Digital | Salalah | Initial investment above £1bn | Agreement stage |
| Hydrom Round 4 | Dhofar | Green power and hydrogen for data centres | EOIs open until February 2027 |
The Salalah figures above come from Oman Observer's Khazaen report, which listed them as context. Round 4 is in Dhofar too, so the governorate is becoming the centre of gravity for large AI loads. That puts the auction alongside earlier targets such as O-Green's plan for 200MW of AI-ready data centres by 2028.
⚠️ The open questions
There is reason for optimism, but a few caveats apply:
- Cost: Al Shidhani himself told TradeArabia that hydrogen markets "will be driven by demand and commercial competitiveness." Data centre operators will compare hydrogen-firmed power with grid electricity on price. The auction's success depends on making that comparison work.
- Expressions of interest are not commitments: Round 4 is at its earliest stage. Firm offtake contracts with data centre operators will matter far more than registrations.
- No disclosed price tags: Neither the Round 3 awards nor the Khazaen campus came with investment values, which makes it hard to judge their scale.
- Timelines: Khazaen's 2028 target depends on approvals, and the Round 3 hydrogen output is not due until 2032.
🇴🇲 The Vision 2040 connection
Vision 2040 calls for economic diversification away from oil and gas, plus a net-zero target for 2050. Round 4 serves both goals at once. It gives the green hydrogen sector local customers, and it gives the digital economy a clean-power story to tell global cloud and AI firms. According to TradeArabia, MTCIT links the Digital Triangle to the next phase of the National Digital Economy Program. The Round 3 consortia have also pledged to train Omani workers, increase local content and bring Omani suppliers into Duqm's new industries, as reported by Oman Observer.
💡 Why this matters for Oman
Other countries can build server halls. What sets a location apart is cheap, reliable, clean power plus subsea cable access, and Oman is trying to package all three in one offer. Round 4 shifts green hydrogen from an export idea to fuel for local digital infrastructure. Projects such as Khazaen show that private developers are already preparing capacity closer to Muscat. If the February 2027 registration window produces real data centre offtakers, Dhofar and Al Batinah could host AI computing that creates high-skilled jobs and supports Omani cloud and AI startups. If it doesn't, the plan will remain a strong pitch without customers. The coming months will show which way it goes.
Tags
Related Articles
Back to School 2025: How Oman's EdTech Revolution is Transforming Every Classroom
As 700,000 students return to school this August, they're walking into AI-powered classrooms, VR labs, and personalized learning systems. Inside Oman's $400 million education technology transformation.
Oman Unveils National AI Strategy 2025-2030: A Blueprint for Digital Sovereignty
The Ministry of Transport, Communications & IT launches Oman's comprehensive AI strategy, targeting 30,000 AI jobs, $5B economic impact, and positioning the Sultanate as the Gulf's AI innovation hub by 2030.
Oman–India Tech Partnership: Driving Innovation Beyond Borders
Discover how growing technology ties between Oman and India are creating new opportunities, from joint AI projects to IT talent exchange and beyond.